Section 6(1), where –
(a) a building owner proposes to excavate, or excavate for and erect a building or structure, within a distance of three metres measured horizontally from any part of a building or structure of an adjoining owner; and
(b) any part of the proposed excavation, building or structure will within those three metres extend to a lower level than the level of the bottom of the foundations of the building or structure of the adjoining owner.
Section 6(2), where –
(a) a building owner proposes to excavate, or excavate for and erect a building or structure, within a distance of six metres measured horizontally from any part of a building or structure of an adjoining owner; and
(b) any part of the proposed excavation, building or structure will within those six metres meet a plane drawn downwards in the direction of the excavation, building or structure of the building owner at an angle of forty-five degrees to the horizontal from the line formed by the intersection of the plane of the level of the bottom of the foundations of the building or structure of the adjoining owner with the plane of the external face of the external wall of the building or structure of the adjoining owner.
The notice period for excavation work which comes within the scope of the Act is 1 calendar month.
If you need guidance or wish to schedule a meeting with one of our surveyors, kindly complete our Consultation Form to provide us with your information. Following this, a team member will reach out to you to organise a consultation with one of our skilled surveyors.
IPWS Surveyors
Bank House
6 Hockley Hill
Birmingham
B18 5AA
Tel: 0800 4880 586
Duty Surveyor: 07462 661 772
Email: info@ipws.co.uk
© 2014-2024 IPWS Ltd. T/A Institute of Party Wall Surveyors