On a tight construction site, use of a tower crane may be the most practical construction method for maximising the footprint of the building and the efficiency of its construction. Developers and their contractors should however be aware of certain key issues likely to flow from use of tower cranes, particularly in densely populated areas:
The use of tower cranes is now commonplace on constructions sites as providing height and lifting capacity, but (and this is particularly important in city centre developments with a small site area) occupying a minimal footprint on the site.
An inevitable consequence of the use of tower cranes on city centre sites is that the jib of the crane will oversail adjacent sites. Even if the operation of the crane can limit the swing of the jib, safety and structural stability require that when the crane is not in use the jib must be left to swing in the wind, giving a circle of oversailing with a radius equal to the length of the jib from the mast of the crane. Any property within that circle will potentially be oversailed.
The basic principle of English law is that a landowner owns all the airspace above the land, to the heavens above. Legislation has given aircraft rights to pass without causing any trespass, but the basic principle holds good nearer the ground. This means that the jib of a tower crane swinging across land owned by an adjoining landowner is trespassing.
If no authority to oversail adjacent properties has been obtained then the developer or the contractor may be faced with injunctions from the adjacent landowners, preventing the oversailing, and hence fundamentally impacting the contractor’s construction methodology. There is case authority1 that an injunction for trespass can be obtained without having to demonstrate any damage, the basis is simply that property rights are being violated.
As with so many development constraints, the key is to address them early enough. In this case, the developer and its advisers can consider the size of tower crane likely to be required, to assess the radius of the likely swing of its jib, and then to approach all landowners whose property may be oversailed to seek their permission to do so, which will be documented in a crane oversail licence. It should be noted that the highway authority is a landowner for this purpose, usually with specific requirements in relation to any oversailing of the highways, predominantly aimed at ensuring public safety. It should also be noted that for the purpose of an oversailing licence, the agreement of both landlords and tenants of the relevant adjoining land may be required.
So what provisions would generally be included in a crane oversail licence?
Adjoining owners may seek a fee to grant the oversailing rights a developer and its contractor need, in addition to payment of the adjoining owner’s costs of putting the licence in place and any other associated fees. Whilst this could be seen as a ransom opportunity for an adjoining owner, in practice case law2 has restricted this. Where a contractor has offered a substantial fee for grant of an oversail licence and had this refused by the adjoining owner, this may inhibit that adjoining owner then seeking an injunction to prevent oversailing, for example resulting in the court awarding an injunction (as trespass is clearly occurring) but then suspending its operation for the duration of the development period, i.e. in effect granting the developer the rights it requires.
This begs the question of what would be considered an appropriate licence fee. There is no specific formula (though certain highway authorities do have set fees for oversailing the roads), but the fee needs to take into account the impact of the use of the tower crane on development costs, compared with the use of other construction methods, and any costs of the adjoining owner arising from the arrangements.
As an adjoining owner, approached for the grant of a crane oversail licence, consider your own future development plans. Now may be the time to secure your own arrangements for the future by making the crane oversail arrangements mutual. Such a mutual arrangement may in practice be far more valuable than receiving a fee for the licence currently requested.
For further information please complete the Advice form.
If you need guidance or wish to schedule a meeting with one of our surveyors, kindly complete our Consultation Form to provide us with your information. Following this, a team member will reach out to you to organise a consultation with one of our skilled surveyors.
IPWS Surveyors
Bank House
6 Hockley Hill
Birmingham
B18 5AA
Tel: 0800 4880 586
Duty Surveyor: 07462 661 772
Email: info@ipws.co.uk
© 2014-2023 IPWS Ltd. T/A Institute of Party Wall Surveyors